CEMENT INDUSTRY

Electrical Energy Consumption

Section / Equipment Electrical energy consumption
(in units / ton of cement)
Mines, crusher & stacking 1.5

Reclaimer,grinding & transport

18.0

Kiln feed, kiln & cooler

22.0

Coal mill

5.0

Cement grinding & transport

23.0

Packing

1.5

Lighting, pumps & services


4.0

Total

75.0

Electrical energy consumers

Mines & Crusher

The first step in the cement manufacturing process is the mining of limestone. Mining has conventionally been with compressed air drilling and subsequently blasting with explosives. The surface miner has recently been developed primarily for mining in locations, which are located close to human inhabited areas. This equipment has proved to be so useful that, they are fast replacing the conventional mining systems.

In one of the new plants, a surface miner was installed and the mining energy consumption (compressors) was avoided. The size of the limestone mined is also lower, resulting in reduction of crushing energy consumption to 0.5 units / ton of cement, as against 1.5 - 2.0 units / ton in conventional plants. The surface miners are presently available for medium limestone. Hence, wherever possible, the surface miner can be installed for achieving energy saving. The operation of surface miner is also environment friendly, with less dust & noise generation.

Hence, consider application of surface miner for soft and medium hard Limestone.

The next step in the cement manufacturing process is the crusher. The choice of crusher type depends on the grindability and the type of down-the-line grinding system.

Typically, for a VRM system/ball mill with roll press system, it is recommended to have a single stage hammer crusher, with a high efficiency screen before the crusher.

Install single stage hammer crusher with high efficiency screen.

The other points to be taken care during the design stage are, the additional auxiliary power consumption. The auxiliary capacity and controls should be designed, such that, the idle power consumption is avoided during operation of the crusher.

Per ton of Limestone Per ton of
Cement
Target power consumption for the crusher
(for medium hard limestone)

1.0 unit

1.5 unit

Transportation of Limestone
The transportation of the mined limestone to the crusher, is normally done through dumpers or trucks. In case of mountainous terrain, the ropeways are installed. The detailed life cycle cost analysis of transportation with dumpers & ropeway indicates that, the ropeway is more beneficial in some cases, where the distances are more than 5 kms. The ropeway calls for higher investment, but the operating costs are much lower. In one of the operating cement plants, the ropeway was installed replacing the dumpers for transportation of limestone from the mines to the crusher in the plant, resulting in substantial benefits. The option of installing a rope-way can also be considered at the design stage.

Hence, consider installation of rope way for limestone transportation, where the distances are more than 5 kms.


Pre-blending system

The pre-blending system plays a vital role in providing a uniform feed to the raw mill. The statistics of the performance of the pre-blending stockpiles in various operating cement plants in the country indicate that, the longitudinal stockpile has a better pre-blending efficiency.

Hence, it is recommended to install a longitudinal pre-blending system.

In locations where the
  1. Rain-fall is more
  2. Raw material is sticky in nature
it is recommended to install closed stockpiles. This will help in avoiding feed failure to the raw mill during the monsoon / rainy seasons.

The target operating pre-blending efficiency should be 10.

Raw mill

The raw mill is a major energy consumer and should be designed based on the grindability and moisture of the limestone available. The Vertical Roller Mill (VRM) has at least 30% lesser power consumption, than the comparable ball mill system. Hence, for upto medium hard limestone, the VRM should be the first choice. Wherever the moisture percentage is also higher, say >15%, VRM should be the first choice. Only in case of very abrasive raw materials or raw materials with higher free silica content, the plant can consider installing a closed circuit ball mill, with a pre-grinding system.

The VRM (wherever the design allows), should be installed with a reject handling / mechanical re-circulation system, to ensure lower pressure drop across the mill.

The energy efficient alternative therefore is to install a VRM with mechanical re-circulation system.

The other aspects to be taken care are

Conveying system - only mechanical conveying systems such as, bucket elevators/belt conveyor should be installed

Classifier - dynamic high efficiency classifier ( cage type classifier ) should be installed

Mill inlet sealing - This is very essential, since majority of air infiltration in an operating plant is through the inlet. The present day plants use either rotary / triple gate seals for the mill inlet. These seals though effective in the initial days, start developing leaks over a period, demanding regular maintenance.
In one of the new plants, a material seal at the VRM has been attempted with satisfactory results. Hence, it is better to strongly consider installation of material seal or reliable triple gate/rotary seals at the design stage itself
High efficiency mill internals (for ball mills)

In the case of ball mills, the present trend is to replace existing mill internals with high efficiency internals (grinding media, liners and diaphragms). This has the following advantages

Higher mill output

Less wear

Lower power consumption (up to 5% reduction is expected)

Lesser maintenance

Hence, all the new plants installing ball mills, should prefer high efficiency mill
internals.

Target power consumption of (VRM) 18 units/ton of cement
for medium hard limestone (or) 11-12 units/ton of limestone

Fans in raw mill

The fans are the major power consumers, next only to the main drive in the raw mill section and hence need attention during the design stage. The major power consuming fans are the raw mill fan and the vent ESP/BH fan (with kiln).

The fans should be high efficiency (> 80%) backward curved fans with variable speed controls.

The typical variable speed mechanisms proposed are
Variable frequency drive (VFD) - up to 250 kW LT drives.
RRC, fluid coupling, SPRS (HT only) - in increasing order of energy efficiency.

The best variable speed systems are VFD for all LT fans and SPRS for all HT fans. The other major decision, whether to adopt a 3-fan system or 2-fan system, should be carefully weighed and taken at the design stage itself. The various conditions and the corresponding decision making table is given below

Operational Characteristics Three Fan System
Two Fan Systems
Entire PH air passes through
the VRM and no flow of air
through by-pass
Not
Advantageous
Will serve
the purpose

Part of PH air is passed through by-pass always

Advantageous
Higher power
consumption

P/H fan/ESP fan operates with damper throttling when R/M is stopped and expected R/M stoppage say >25% of time

Advantageous
and lower power

Higher power
consumption

The other major decision is to decide the excess margin for the fans. The closer the operating point to the design point, the higher will be the efficiency of the fan. However, a safety margin is required to meet the contingency requirements.

The fans are to be designed typically with 15 % margin over the operating condition.

Raw mill and kiln main dust collection system

The Electro Static Separator (ESP) has been conventionally used for collecting the dust in the kiln and raw mill circuits. The operating efficiency of the ESPs are normally around 99.5 %. The operation of the ESP also depends on the CO content of the flue gas. Whenever the CO content goes beyond 0.6 %, the ESP trips. The amount of time the tripping occurs is less; it nevertheless, leads to particulate emissions. With the increased emphasis on the environmental regulations, it is necessary to have a dust collection system, that is say 99.9 % efficient and operate continuously.

The present trend has been to install bag houses for the kiln and raw mill exhaust. The comparisons of the ESP and bag house are as below

  1. The bag house has a pressure drop of about 150 mm Wg as against 20 - 40 mm Wg in the ESP. Hence, the power consumption of the exhaust fan is higher.
  2. The ESP trips, whenever the CO content goes beyond 0.6 %, while the operation of the bag house is not dependant upon the CO value.
  3. The collection efficiency of the bag house is much higher at 99.9%, while that of the ESP is marginally lower. However, presently ESP's with efficiencies of 99.9% require higher investments.
  4. The ESP requires conditioning with power consumption for the GCT pump and screw conveyors.
  5. The GCT in the ESP system needs water for conditioning, while the bag house does not need water.

Hence, at the design stage itself, the decision to install the Bag house or ESP has to be taken, after carefully weighing the above aspects.

Blending and homogenisation

This is a very important operation having a major bearing on the operation of the kiln and the thermal energy consumption of the kiln. The comparisons of the effectiveness & energy efficiency of various systems indicate that, the continuous blending & storage system is more efficient.

Hence, it is recommended to install a continuous blending & storage system. The target blending efficiency should be 10.

Kiln and pre-heater

Kiln feed conveying


Kiln feed conveying should be carried out by mechanical bucket elevator, as pneumatic conveying is more energy consuming and also adds false air to the system. The pneumatic conveying system consumes about 1 unit / ton of kiln feed, as against 0.25 units / ton of kiln feed for a mechanical conveying system.

Hence, it is recommended to install a mechanical conveying system.

Pre-heater - stages & sizing

The more the number of stages in a preheater, the higher the thermal efficiency of the system.

In the older plants, the conventional cyclones offer a pressure drop of 550 to 600 mm wg resulting in higher power consumption of the pre-heater fan. Presently low-pressure drop cyclones, having a pressure drop of 380 - 420 mm wg are available. With the installation of these low pressure drop cyclones, it is possible to achieve a pre-heater fan power consumption of about 6 units / ton of clinker, as against the present consumption of more than 8 units / ton of clinker. The target pre-heater fan air flow capacity should be below 1.8 Nm3/kg of clinker.

The margins in all the sections of the plant, also influence the energy efficiency of the plant. It is recommended that all the equipment in the pre-heater system, be designed for a kiln loading of 5 ton/m3/day.

Coal conveying system

The coal after grinding in the mill, is conveyed pneumatically to the kiln & calciner for firing. Generally, identical conveying equipments are used for both calciner and kiln. The coal fired in the calciner is about 50 % more than that fired in the kiln. Correspondingly, the capacity of the conveying system and the blower are lower for the kiln firing. The installation of a lower capacity conveying system, reduces the quantity of the ambient air entering the kiln. This increases the secondary air by an equivalent quantity, resulting in increased thermal efficiency. Hence, by design separate right capacity conveying systems should be installed for kiln & calciner.

Install separate right capacity coal conveying system for kiln & calciner .

Water sprays


Water spray systems can be installed, particularly in cooler vent, pre-heater outlet or other areas, where further utilisation of heat is not required. The volume of the gas can be reduced by spraying of water, which ultimately results in reduction of fan power consumption. Presently, water spray systems, which can reduce temperature by more than 100oC in a small area, are available. These systems can aid in reducing the power consumption of the exhaust fans.

GCT water pumps

Water is sprayed in GCT (located before R/M or in the by-pass line) through high pressure pumps. The capacity of pumps required depends on the operation of raw mill and coal mill. The water requirement will be maximum, when none of the hot air users are in operation. The water requirement will be least, when all hot air users are in operation. Hence, it is better to install pumps of different capacities to suit both the different requirements.

Install two GCT pumps of different capacities to meet the raw mill operation and stoppage condition.

Coolers

The cooler is a critical equipment used for cooling and also to recuperate the heat back into the kiln system. This has a major bearing on the thermal efficiency of the system. This is being dealt with in Section-5.4. The cooler is also a major consumer of electrical energy. The major energy consumers are the cooler fans.

It is recommended to install high efficiency backward curved fans for cooler, with Variable Frequency Drives (VFD) for all the fans.

Target energy consumption - 5 units / ton of clinker


Coal section

The coal is generally procured from the coalfields through rail or road, crushed, ground to fine powder and then used in the mill. The coal receipts vary in quality continuously. Hence, it will be better to install a longitudinal pre-blending stockpile for coal also. The installation of pre-blending stockpile for coal will ensure uniform quality of coal feed to the kiln.

Install pre-blending stockpile for coal.

The coal mill is also a major energy consumer. Presently, majority of the coal mills are air-swept ball mills. The VRM has been installed in some of the modern plants, with at least 40% lower energy consumption, in comparison to the conventional air-swept ball mills, used in older cement plants. Hence, it is recommended to install vertical roller mills for coal grinding.

Install VRM for coal grinding.

Fine coal bins

The calciner can accept coarser coal, in comparison to the kiln. Hence, it is recommended to have separate fine coal hoppers, for kiln coal and calciner coal. This will enable differential grinding of coal for calciner & kiln.

Install separate bins for calciner and kiln.

Fans in kiln & coal mill

The fans are major power consumers in the kiln and pre-heater system. Hence, by design the fans should be of higher efficiency (>80%) and equipped with a variable speed mechanism for speed control. The typical variable speed arrangements for the fans in the kiln and coal mill sections are as below


Fan Type of veriable speed drive (VSD)
P H fan SRPS/GRR/LRS

RM fan/ESP fan

SPRS/GRR/LRS

Cooler vent fan

SPRS/DC/Fluid coupling/ GRR/LRS

Cooler fans

VFD
Coal mill fans

VFD/GRR (or) fluid coupling for HT

The VSDs are given in the order of reducing efficiency.

Cement mill

The cement mill is another major energy consumer in a cement plant. In the present operating plants, majority of the cement mills are open circuit ball mills. In some of the plants, closed circuiting has been done, to increase the capacity & reduce the energy consumption. The installation of the pre-grinding system, has also been taken up in some plants, with substantial benefits. Very recently, the VRM has also been installed for grinding of cement in three cement plants in India. The results reported by one of the plants (23-24 units/ton of OPC-43) is very encouraging.

Hence, every new plant should go for either a VRM or a ball mill with pre-grinding system & high efficiency separator.

The VRM should have a high efficiency separator and mechanical re-circulation system. The ball mill if installed, should have high efficiency internals (grinding media, liner plates, diaphragm). The conveying of cement to the silo should be through a mechanical conveying system.

Utilise mechanical conveying for cement.

Target power consumption for OPC - 43 grade cement are as follows

VRM - 23 units / ton of cement
Ball mill with roll press - 27 units / ton of cement
Ball mill ( closed circuit ) - 29 units / ton of cement

Cement silo and packing plant

The cement silo should have a blower extraction system, to reduce the power consumption. The packing should be through an electronic packer, for accurate weight and reduced energy consumption.

Target power consumption - 1.5 units / ton of cement


Introduction on Indian Cement Industry

Target Energy Consumption

Thermal energy consumption

Process control system

Energy efficiency aspects
My GBC Publications FAQ Feedback Contact Us

©Designed and developed by InPractice Technologies